The City of Monticello, Iowa
IN THE NAME AND BY THE AUTHORITY OF THE CITY OF MONTICELLO, IOWA
RESOLUTION #2020-95
To approvepayment to Midwest Concrete Inc. related to Willow Park Highway 38 Trail Extension.
WHEREAS, Midwest Concrete Inc. contracted with the City to install a trail extension along Highway 38 between the Hwy. 38 Bridge and the Oakwood Cemetery entrance, and
WHEREAS, Midwest Concrete, Inc. has satisfactorily completed the project, with final grading and seeding to be completed by the City of Monticello, and
WHEREAS, The Original bid totaled $78,945.55 and after adjustment for actual quantities and three minor changes to the final project design, the final invoice totals $80,750.11, and
WHEREAS, The Council finds that the changes were reviewed by City Staff and the Contractor and that all changes / modifications were appropriate, and that the invoice should be approved for full and final payment in the amount of $80,750.11
NOW THEREFORE, BE IT RESOLVED that the City Council of Monticello, Iowa does hereby approve Midwest Concrete, Inc.’s pay request in the total amount of $80,750.11 related to the Willow Park Highway 38 Trail Extension.
IN THE TESTIMONY WHEREOF, I have hereunto subscribed my name and caused the Great Seal for the City of Monticello, Iowa to be affixed. Done this 8th day of September, 2020.
Brian Wolken, Mayor
Attest:
Sally Hinrichsen, City Clerk