RESOLUTION #19-81
Resolution to approve additional payment to Anderson Ladd, Inc. related to Berndes Center floor project.
WHEREAS, The City of Monticello is the owner of the Monticello Berndes Center, a multi-use facility that has for many years been served by a multi-use “Sport Court” flooring system, and
WHEREAS, The City Council previously contracted with Anderson Ladd, Inc. to install a new flooring surface in the Berndes Center, and
WHEREAS, Anderson Ladd, Inc. installed a new floor, however, due to errors in the initial installation a significant retainer was withheld pending finalization of corrective steps, and
WHEREAS, The originally approved cost totaled $105,694, additional sealing was required at a cost of $22,000, and another paint color was added to the plans adding $2,340 in cost, and
WHEREAS, Payments to date have been made in the amount of $11,000, $95,770.50, and $20,923.50, leaving a balance of $2,340, and
WHEREAS, The Council recently approved Resolution 19-72 approving the final payment to Anderson Ladd, after which Anderson Ladd provided supplemental information supporting payment of the additional sum of $2,340, said amount being tied to a previously approved change to the floor paint scheme.
NOW, THEREFORE, BE IT RESOLVED that the City Council of Monticello, Iowa does hereby approve of the release of the retainage and approve the additional payment to Anderson Ladd as outlined above in the amount of $2,340.
IN TESTIMONY WHEREOF, I have hereunto subscribed my name and caused the Great Seal of the City of Monticello, Iowa to be affixed hereto. Done this 3rd day of June, 2019.
Brian Wolken, Mayor
Attest:
Sally Hinrichsen, Monticello City Clerk