Approving Pay Request #6 in the amount of $15,681.23 and Change Order #2 in the amount of $1,344 submitted by Taylor Construction, Inc. Re: 2018 E. 1st Street Bridge Replacement Project.
WHEREAS, Taylor Construction, Inc. contracted with the City to replace the E. 1st Street Bridge lying over Kitty Creek, and
WHEREAS, Taylor Construction, Inc. has submitted their 6th pay request in the amount of $15,681.23 which reflects 3% retainage, with total retainage held to date after this payment in the amount of $14,826.04, and
WHEREAS, Taylor Construction, Inc. has also submitted Change Order #2 in the amount of $1,344 related to additional mobilization and PCC cold weather protection, and
WHEREAS, The City will be reimbursed a large portion of this expense after the submission of a request for reimbursement through the IDOT, with the funding coming from Federal Bridge Funds, and
WHEREAS, The City Engineer has reviewed pay request #6 and recommends its approval.
NOW THEREFORE, BE IT RESOLVED that the City Council of Monticello, Iowa does hereby approve Pay Request #6 submitted by Taylor Construction, Inc. Re: 2017 E. 1st Street Bridge Replacement Project, in the amount of $15,681.23 and Change Order #2 in the amount of $1,344 and authorizes payment in the amount of $15,681.23, maintaining a 3% retainage in the amount of $14,826.04.
IN THE TESTIMONY WHEREOF, I have hereunto subscribed my name and caused the Great Seal for the City of Monticello, Iowa to be affixed. Done this 16th day of July, 2018.
Brian Wolken, Mayor
Attest:
Sally Hinrichsen, City Clerk