THE CITY OF MONTICELLO, IOWA
RESOLUTION #12-45
Resolution approving pay request from Monk Construction related to
FBO rehabilitation project.
IN THE NAME AND BY THE AUTHORITY OF THE CITY OF MONTICELLO, IOWA
WHEREAS, The City previously hired Monk Construction to perform pre-determined renovations to the City owned FBO Building at the Monticello Airport, and
WHEREAS, work by Monk Construction and its’ subcontractors has progressed to a point where Monk has submitted his first pay request in the amount of $35,296.80, representing 70% completion of the work being performed by Monk, approximately 50% of the work being performed by the electrician, and nearly all of the work to be performed by the HVAC/plumbing contractor, and
WHEREAS, The City Administrator and the Airport Manager have both visually inspected the facility and find that the work performed to date appears to be consistent with the invoiced work and based thereon recommend that the first pay request of Monk Construction should be paid.
NOW THEREFORE BE IT RESOLVED by the City of Monticello, through its’ City Council, in session this 19th day of March, 2012, that the City Clerk is hereby directed to make payment to Monk Construction in the amount of $35,296.80 and to thereafter seek appropriate reimbursement from the State of Iowa through the Iowa DOT vertical infrastructure program.
IN TESTIMONY WHEREOF, I have hereunto subscribed my name and caused the Great Seal for the City of Monticello, Iowa to be affixed. Done this 19th day of March, 2012.
Dena Himes, Mayor
Attest:
Sally Hinrichsen, City Clerk